CONSTRUCTION UPDATE FOR WEEK OF JANUARY 2ND
The following is scheduled to occur this week:
1. The mason’s will be finishing up their work this week. They are working on the walls that will serve as the storage room, meeting room which are also the spaces that will be designated as weather safe rooms. These rooms will have a poured concrete slab roof and FEMA approved doors to each of the rooms. The cinder blocks have rebar through them and were filled with hand-poured concrete.
2. Steel will be set this week.
3. Next week the framers will begin closing in the walls.