The following is scheduled to occur this week:
– Painters are on site this morning and will begin painting today
– Will continue with duct work, plumbing and finishing of drywall
– Siding continues
– Block continues to go up
– M6 will be on site Wednesday to saw cut the floor in the Boiler Room for the floor drains
– The last load of millwork and cabinets will arrive today
– Millwork installation will begin on Monday, 4/24
– SW Cabling was on site last week and rerouted the CAT5 cable in the Procedure Room.
– They will sheet rock the ceiling in the Procedure Room this week and then begin finishing. Hutton has the plate that needs to go up for the light so the sheet rock can be completed.
– Hutton is working on a solution to improve the water drainage from the building on the (N) side of the Clinic.