Coloring Contest Winners

Winners from our Women’s Health Banquet Coloring Contest:

Winning pictures are on display in the Minneola Community Clinic.

CONSTRUCTION UPDATE FOR THE WEEK OF APRIL 17TH

The following is scheduled to occur this week: – Painters are on site this morning and will begin painting today – Will continue with duct work, plumbing and finishing of drywall – Siding continues – Block continues to go up – M6 will be on site Wednesday to saw cut the floor in the Boiler… Continue Reading

CONSTRUCTION UPDATE FOR THE WEEK OF 2/4/17

CONSTRUCTION UPDATE FOR THE WEEK OF 2/4/17 The following is scheduled to occur: – The mason’s will be on site this week to start on the brick that goes out front. – Roofing will be put on this week. – Framers will continue working inside the space. – The plumbers and electricians continue to work… Continue Reading

CONSTRUCTION UPDATE FOR THE WEEK OF JANUARY 23RD

CONSTRUCTION UPDATE FOR THE WEEK OF JANUARY 23RD The following is scheduled to occur this week: – They will be pouring the concrete slab over the Safe Room spaces this week. – The Framers are beginning today. – The Masons will begin their work next week, topping out the Safe Room and then will move… Continue Reading

CONSTRUCTION ACTIVITY FOR WEEK OF JANUARY 9TH

CONSTRUCTION ACTIVITY FOR WEEK OF JANUARY 9TH All: I hope you have all noticed by now that they have started putting up the steel columns and will begin connecting those columns this week. They will have to further notch out the two outside corners of the lab space to make room for columns in each… Continue Reading

CONSTRUCTION UPDATE FOR WEEK OF JANUARY 2ND

CONSTRUCTION UPDATE FOR WEEK OF JANUARY 2ND The following is scheduled to occur this week: 1. The mason’s will be finishing up their work this week. They are working on the walls that will serve as the storage room, meeting room which are also the spaces that will be designated as weather safe rooms. These… Continue Reading

ACTIVITY FOR THE WEEK OF 12/19/2016

ACTIVITY FOR THE WEEK OF 12/19/2016 All: The construction activity report for this week is as follows •Tomorrow the last concrete pout to finish the slab will occur. •Masonry block will be delivered and they will start laying on 12/27/2016 •Structural steal will start going up next week. Continue Reading

CONSTRUCTION UPDATE FOR THE WEEK OF NOVEMBER 14TH

CONSTRUCTION UPDATE FOR THE WEEK OF NOVEMBER 14TH – They will continue digging footings this week – Around 10:00 this morning, they will begin pouring concrete and are expected to pour 80-100 yards of concrete. This will take care of part of the front of the new addition, up the west hallway, and then across… Continue Reading