• Minneola-District-Hospital-Lobby
  • Minneola-District-Hospital-Wing-Construction

CONSTRUCTION UPDATE FOR THE WEEK OF JANUARY 23RD

CONSTRUCTION UPDATE FOR THE WEEK OF JANUARY 23RD

The following is scheduled to occur this week:

– They will be pouring the concrete slab over the Safe Room spaces this week.

– The Framers are beginning today.

– The Masons will begin their work next week, topping out the Safe Room and then will move to laying the brick by what will be the new Front Entrance to the Hospital.

– The electricians will continue working in the tunnel and will also continue with the work they need for the new sterilize that is to be installed soon.

– There will be some saw cutting inside the Hospital for the new drain that will be needed for the sterilizer. If needed, this can be done on a Saturday so not to disrupt procedures.

– The start date for the OR renovation will be February 27th!